Canyon Ridge High School

CRHS and Other Bond Levy Projects Update

In an effort to keep the public up-to-date with accurate data regarding the bond building budget and projects, the following information is provided:

1. Canyon Ridge High School construction started in July 2007 is on schedule and, barring some unforeseen circumstances, will be finished and ready for school in the fall of 2009. The current schedule will allow for “move in time” and give students and staff time to get acquainted with the new building.

2. Seven building improvement projects or remodels are complete or will be complete during the fall of 2008. During 2007 - Lincoln ADA elevator, Perrine and Morningside site safety projects were constructed. In 2008 the TFHS football bleachers and chemistry lab remodel, as well as Bickel and Perrine multi-purpose rooms will be ready and available for use.

3. Seventeen projects including 3 elementary school multi-purpose rooms, improvements at TFHS and a number of remodeling projects in the various schools are still scheduled to be designed and completed. The remaining projects will be placed on the schedule for construction over the next two to three years. All projects that were included in the bond levy package will be complete; it will just take longer.

4. Inflation has impacted the project since its inception. According to government statistics, between 2003 and 2008 the cumulative inflation rate for construction projects has reached over 30%.

5. Unexpected costs have also impacted the bond budget. Major items like Park View Street and the 48” concrete piping of the irrigation canal running along the boundary of the property of Canyon Ridge High School were unexpected expenses that were unknown until the project was underway. The total cost of these two items was $1,169,615. There have been a number of smaller items that have been added to the project costs.

6. Numerous bids were reviewed and rebid to help reduce costs. Some examples included: elimination of metal roofing, less landscaping, less concrete on exterior items, narrower sidewalks, elimination of mow strips; fewer outbuildings; no dugouts for softball and baseball; less costly running track surface; fewer stadium seats and no bleachers in the upper level of the gymnasium. Numerous other items are being reviewed to determine the impact on cost, functionality and quality of the building.

7. The taxpayers will not be asked to approve an additional levy to pay for the current projects.

8. The construction management method for construction supervision used by the district is designed to provide the district with more involvement and control over the project, costs and quality of the building.

9. Contractors who want to be involved in the construction phase of the building project go through a bid process. Bids are submitted, opened and the lowest responsible bidder is awarded a contract. The contractor is bound to honor the amount of the bid submitted for the work to be performed. The bid process is regulated through parts of the Idaho Code.

10. Interest earned from the bond levy funds will be used to help in the payment of building projects. The estimated interest to be contributed to the bond fund is approximately $4.5 million.

11. Two parcels of land adjacent to the CRHS site have been appraised for $2.6 million and when that land is sold, the proceeds will be placed in the bond fund.

12. Through tough decisions, careful scrutiny and value engineering, the bond budget is currently $4 to $5 million over budget as compared to $6 to $7 million over budget as publicized last December.

13. Projects not funded by the bond will be worked into our plant facilities fund long-range plan.

The Twin Falls School District makes every effort to carefully manage the bond building projects and to ensure the greatest return for the dollars spent. Taxpayers and patrons provide the funds for the district, and it our intent to maximize the investment in our buildings and programs to enable staff and students to benefit in their educational experience. We appreciate the confidence and support of the people who live in the Twin Falls School District.

CHECK OUT THE DESIGN OF CRHS

CHECK OUT SOME CRHS AERIAL PHOTOS

                                         

Follow our Progress

 

Click on the image to enlarge it